Skip to content
Victaura

Value-Add Methodology

Permit Calendar: Lake Como, Day by Day

A dated permit file is the cheapest proof of execution capacity, and almost nobody publishes one. This paper rebuilds the Lake Como calendar from the statutes. It names each body, the day its clock starts, the days the law grants it and the events that stop the clock, then sets the arithmetic against what practitioners report. The gap between the two is the underwriting fact.

Victaura Research · · 21 min read ·

Corrected on , details at the end

Illustration of a desk calendar with blank pages, a heavy rubber stamp and a rolled architectural drawing, a lake window behindIllustration

Key takeaways

  • - The ordinary landscape track sums to 105 statutory days on paper: 40 days at the comune, 45 at the Soprintendenza, 20 at the comune (D.Lgs 42/2004 Art. 146; Victaura arithmetic).
  • - The building permit adds 90 statutory days, 60 of instruction and 30 for the final act, so the sequential ceiling is about 195 days; 255 if the instruction term is doubled (DPR 380/2001 Art. 20; Victaura arithmetic).
  • - The simplified track has a peremptory 60-day limit with terms of 10, 20, 20 and 10 days, but only for a closed list of low-impact works (DPR 31/2017 Artt. 10 and 11).
  • - Silence is narrower than its label: if 60 days pass without an opinion the comune may proceed, and the Consiglio di Stato held in 2021 that Article 17-bis silence-assent does not cover the instruction phase (Cons. Stato no. 2640/2021, reported).
  • - Clock-stoppers include a one-time 30-day suspension, a 10-bis notice with 10 days for observations, and a one-time permit interruption within 30 days of filing (Legge 241/1990 Artt. 2 and 10-bis; DPR 380/2001 Art. 20).
  • - The landscape authorisation is effective for five years, counted from the day the building title becomes effective unless the delay is the applicant's, with one further year to finish works begun within them (D.Lgs 42/2004 Art. 146 c.4).
  • - No public dataset measures actual durations on the lake; the 12-24 month figure for a substantial restoration is an unaudited industry estimate, roughly 1.9 to 3.7 times the ceiling (Victaura Research companion paper; Victaura arithmetic).
  • - The useful diligence item is the dated file: protocol dates, requests for additions, opinion and permit dates, from which the elapsed-versus-statutory ratio, the number of stops and the administration-versus-applicant split can be computed.
On this page (10)

Why a dated calendar

A dated calendar is the cheapest proof of execution capacity that an allocator can ask for, and almost nobody publishes one. Lake Como schemes are usually described in the language of ambition. Very few are described in protocol numbers, filing dates and opinion dates. Yet the permit file is the one document in a restoration thesis that is produced by third parties, stamped by public bodies and dated by law. It cannot be flattered.

This paper reconstructs the calendar from the statutes, not from anecdote. It covers the ordinary autorizzazione paesaggistica under Article 146 of D.Lgs 42/2004, the simplified track under DPR 31/2017, and the permesso di costruire under Article 20 of DPR 380/2001, read for a lakefront intervention in Lombardy. It names each body, the day on which its clock starts, the term the law gives it and the events that stop that clock.

The companion paper on the landscape constraint covers the stack of layers. This one covers only time. The 300-metre band under Article 142, the regional plan and the municipal regolamenti are set out there. Here the question is narrower. In what order do the bodies act, how many days does the law allow each of them, and what does the sum come to before any clock is stopped? The answer is a ceiling, and a ceiling is a useful thing to hold.

One caveat governs everything that follows. The statutory terms below are measured in the plain sense that they are written in law. The durations that projects actually take are not measured in any public dataset we could find for the lake. Wherever this paper speaks of actual duration it says industry estimate, and it says so every time. The reader should treat the theoretical calendar as the fastest lawful path and nothing more.

105 days
ordinary landscape track on statutory terms alone: 40 days comune, 45 days Soprintendenza, 20 days comune. Victaura arithmetic on the statute, before any suspension. It is a ceiling on paper, not an observed duration.

Source: Italy, D.Lgs 42/2004, Articolo 146, commi 5-9

Day 0 to day 40: the comune

The calendar starts at the comune, not at the Soprintendenza. In Lombardy, Regional Law 12/2005 attributes the landscape authorisation function to municipalities and unions of municipalities (Article 80) and requires the authority to set up a commissione per il paesaggio (Article 81). The application is lodged with the comune on whose territory the villa stands. Day 0 is the date the application is received, and every later term is counted from a date that the file must be able to prove.

Within 40 days of the application the comune must do two things. Under Article 146, paragraph 7, it verifies the conformity of the intervention with the landscape plan, and it sends the documentation to the Soprintendenza with a reasoned proposal. In the ordinary track the opinion of the local commission is acquired inside that window. Under the regional law that opinion is mandatory but not binding on the comune. The commission's meeting calendar therefore sits inside the 40 days, not beside them.

The completeness check is where the first clock can stop. The Soprintendenza verifies that the file meets the national documentation standard (the DPCM of 12 December 2005, as its own guidance cites it) and may ask for additions, which suspends the terms. Article 2, paragraph 7 of Law 241/1990 separately allows a term to be suspended once, for no more than 30 days, to obtain information the administration does not already hold. One well-timed request can move a whole calendar by a month.

Day 40 is the first date an allocator can check against a document. The transmission to the Soprintendenza leaves a protocol number and a date, and the applicant is informed of it. If the file shows a transmission at day 38, the comune performed to the statute. If it shows day 140, that difference is information about the comune, about the file, or about both. Asking for the date costs nothing, and the answer costs the counterparty nothing if the file is clean.

Day 40 to day 85: the Soprintendenza

From the day the Soprintendenza receives the file, it has 45 days to issue its opinion. Article 146, paragraphs 5 and 8 set the term at forty-five days from receipt of the documents. For Lake Como the body is the territorial Soprintendenza of the Ministry of Culture for the provinces of Como, Lecco, Sondrio and Varese (SABAP CO-LC). Its clock starts on receipt, not on the application date, so any gap between day 0 and the transmission is added to the calendar without appearing in the Soprintendenza's own count.

The opinion is binding, which is why this step decides the calendar. Soprintendenza guidance states that the opinion is binding as long as the municipal planning has not been adapted to the landscape plan. Whether and when each lake comune has aligned its Piano di Governo del Territorio with the regional plan is therefore a variable in the calendar. We could not verify it comune by comune, and we say so in the disclosed weaknesses below.

A negative view arrives first as a notice, not as a refusal. Where the opinion would be negative, the Soprintendenza sends the notice under Article 10-bis of Law 241/1990. The applicant has ten days to submit written observations, and the terms stay suspended until ten days after the observations are filed. This is the point at which designs change. A scheme revised after a 10-bis notice is a scheme whose clock has partly restarted, and the file will show it as a second dated exchange.

The Soprintendenza can also stop the clock at the door. It verifies completeness and can request additions, which suspends the procedure. In the ordinary track, then, day 40 is not a promise that day 85 follows. It is the earliest date on which the 45-day count can begin, and it is the count that is easiest to interrupt. The theoretical calendar assumes a file that was complete on first submission. That is an assumption, not a base rate.

The statute gives every body a number of days. The file shows how many it took. The difference is the only underwriting fact nobody publishes.

Victaura Research

Day 85 to day 105, and what silence does

The comune has 20 days from receipt of the opinion to decide. Article 146, paragraph 8 sets the term. With a positive opinion the authorisation follows, and Soprintendenza guidance states it is effective immediately. On the arithmetic, the ordinary track closes at day 105 (40, then 45, then 20). That is the first of the two numbers this paper carries forward.

The statute also writes the failure case. Under paragraph 9, if 60 days pass from the Soprintendenza's receipt of the documents without an opinion, the comune decides on the application anyway. On the calendar above that is day 100. The market calls this silence-assent, and the label overstates it. What the statute allows is that the comune may proceed. It does not say that the authorisation is granted.

The Consiglio di Stato has narrowed the label further. In judgment no. 2640 of 29 March 2021, as reported by a law-firm commentary, it held that the silence-assent rule of Article 17-bis of Law 241/1990 does not apply to the instruction phase of the Article 146 procedure. The comune must still carry out the full investigation and prepare the proposal. Silence does not remove the work. It changes who may decide when the co-deciding body does not speak.

Late opinions are a live legal question, and we do not resolve it. On the Article 146 procedure itself, the Consiglio di Stato (Fourth Section, judgment no. 2487/2023) held that a Soprintendenza opinion sent after the 45-day term remains effective but is no longer binding, so the authority deciding the application may set it aside and must give its own reasons if it follows it. The same judgment records the opposite line of earlier rulings, under which a late opinion loses the effect the law gives it, binding force included. On the judgment's own account, neither line keeps a late opinion binding. A first-instance judgment, TAR Campania no. 4406/2025, on the related Article 167 compatibility procedure, is reported to have held that an opinion issued far beyond its 90-day term lost its binding force. That is one ruling, on a different procedure, reported through a trade publication. Treat it as directional. It does not show that a lakefront comune will proceed without the opinion, and no principal should underwrite a schedule on the assumption that it will.

The clock-stoppers

The theoretical calendar is a ceiling only if nothing stops the clock, and the law lists what can. Three mechanisms recur. A one-time suspension of up to 30 days to acquire information, under Article 2, paragraph 7 of Law 241/1990. The 10-bis notice, which gives the applicant ten days for observations and suspends the term. And, in the building permit, a one-time interruption within 30 days of filing under Article 20, paragraph 5 of DPR 380/2001.

Stacked, they move the calendar in blocks of weeks. Take the ordinary landscape track. Add one 30-day suspension for additions and one 10-bis exchange, in which the applicant has ten days to reply and the term resumes ten days after the reply, and 105 days becomes as much as 155 before any redesign time is counted. That figure is Victaura arithmetic on the statutory ceilings. It is an illustration of how the terms compound, not an observation of any file.

The asymmetry that matters is who holds the pen. Statutory terms bind the administration. The time an applicant needs to answer a request is the applicant's own, and on a heritage villa the answer may need archival research, structural checks and a fresh survey. The clock the law stops is the administration's. The clock that keeps running is the carrying cost of the asset, and it is borne by the principal.

A calendar with no stop in it is either an exceptional file or an incomplete one. An allocator reviewing a dated calendar should expect to see at least one suspension or exchange. A file that shows none deserves a question. It may reflect a complete first submission and a responsive comune. It may equally reflect a calendar that has been tidied for presentation. The dated protocol records, not the summary, settle which.

Horizontal bar chart of the cumulative statutory ceiling, in days from the application, at the end of each step of the ordinary Lake Como permit track: application filed at day 0, proposal to the Soprintendenza by day 40, binding opinion by day 85, landscape authorisation by day 105, highlighted, building permit proposal by day 165 and building permit final act by day 195, highlighted. These are ceilings on statutory terms, not observed durations.
Cumulative statutory ceiling, in days from the application, at the end of each step of the ordinary Lake Como track, before any clock is stopped. Day 105 (landscape authorisation) and day 195 (final permit) are highlighted. Victaura arithmetic on the statutory terms; ceilings, not observed durations.
Chart data
StepCumulative day (ceiling)
Application filed0
Proposal to Soprintendenza40
Binding opinion85
Landscape authorisation105
Building permit, proposal165
Building permit, final act195

Source: Italy, D.Lgs 42/2004 Art. 146; DPR 380/2001 Art. 20; Legge 241/1990 Artt. 2 and 10-bis; Regione Lombardia LR 12/2005; Victaura arithmetic

StepBodyStatutory termCumulative day (ceiling)What can stop the clock
Application filedComune (Lombardy, LR 12/2005 Art. 80)Day 00Pre-filing design work sits outside the count
Verification, commission opinion, proposal to SoprintendenzaComune and commissione per il paesaggio40 days from the application40Request for additions, once, up to 30 days (L. 241/1990 Art. 2 c.7)
Binding opinionSoprintendenza45 days from receipt; comune may proceed at 6085Request for additions; 10-bis notice with 10 days for observations
Landscape authorisationComune20 days from the opinion105A negative opinion ends the procedure in refusal
Building permit, instruction and proposalComune, responsible officer60 days from filing; doubled if particularly complex165One interruption within 30 days of filing (DPR 380/2001 Art. 20 c.5)
Building permit, final actComune, dirigente30 days from the proposal; 40 after a 10-bis notice195Silence-assent forms if the landscape authorisation is already issued and valid (DPR 380/2001 Art. 20 c.8)
The ordinary Lake Como calendar on statutory terms, with the events that stop each clock. Cumulative days are Victaura arithmetic assuming the permit follows the authorisation; they are ceilings, not observed durations.

The short track and its limits

DPR 31/2017 replaces 105 days with 60, but only for a closed list of small interventions. Article 10 sets a peremptory 60-day term from receipt of the application, and Article 11 sets the steps inside it. The individual terms are short. The administration has ten days for its initial verification and a single request for documents, and the applicant has ten days to answer. The comune then has 20 days to send a reasoned proposal, the Soprintendenza has 20 days for its binding opinion and the comune has ten days to decide.

A substantial lakefront restoration will usually not qualify. As set out in the companion paper, material changes to openings, roofline or external finishes fall in the ordinary track. The simplified list is for small-scale changes to existing buildings. Which track applies is the first decision in the calendar, and Article 11 gives it to the administration on receipt. An applicant who plans on 60 days and is moved to the ordinary track faces a statutory ceiling of 105 days rather than 60, plus the time the simplified filing has already used.

In the simplified track the local commission is optional unless regional law says otherwise. Article 11 provides that the opinion of the local landscape commissions is not mandatory in the simplified procedure, save for what regional laws provide. Lombardy has provided otherwise. Regional Communication 144/2018, as reported by Edilportale, states that under LR 12/2005 the commission's opinion remains mandatory in the simplified procedure as well, and that omitting it is a defect of legitimacy. On the lake the commission's meeting calendar therefore sits inside the short track too.

The short track has a longer tail on the negative path. If the administration's evaluation is negative it says so within ten days and the applicant has 15 days to submit observations or a revised project. If the Soprintendenza denies the proposal, the applicant again has 15 days before a final decision period of 20 days. The headline 60 days is the term for a clean, positive file. It is not the term for a contested one.

60 days
peremptory outer limit of the simplified landscape procedure from receipt of the application, with terms of 10, 20, 20 and 10 days at each step. Measured in law; it applies only to the closed list of low-impact interventions.

Source: Italy, DPR 31/2017, Articoli 10 e 11

After the authorisation: the building permit and the expiry clock

The landscape authorisation is not the end of the calendar. It is the entry ticket to the second one. The authorisation is a separate act, and the building title on a protected site cannot be issued without it. The permesso di costruire then runs its own terms under Article 20 of DPR 380/2001. The responsible officer has 60 days from filing to complete the instruction and formulate a proposal, acquiring the other assents required under Article 14 and following of Law 241/1990.

The permit's decision term is 30 days, or 40 after a 10-bis notice. Paragraph 6 gives the dirigente 30 days from the proposal to adopt the final act. Paragraph 5 allows one interruption of the instruction term, within 30 days of filing, to request further documents. Paragraph 7 doubles the terms of paragraphs 3 and 5 for particularly complex projects, which moves the instruction term from 60 to 120 days. A restoration on a protected lakefront is a plausible candidate for that label, but whether a given comune applies it is a matter for the file.

On a constrained site, silence builds the permit only once the landscape authorisation is in hand. Under Article 20, paragraph 8, as amended in 2020 and 2025, silence-assent forms on a permit application when the term for the final act lapses without a reasoned refusal. Where the property is subject to landscape, heritage, environmental or hydrogeological constraints, the conference-of-services rules of Article 14 and following of Law 241/1990 apply, but silence-assent still forms if the authorisations for those constraints have already been issued on the same drawings and are still valid. A lakefront villa inside the 300-metre band is constrained by law, so in the sequential calendar above, with the authorisation obtained first, the permit can be formed by silence. The comune must then certify, within 15 days of a request, that the terms have lapsed, and that certificate, with the authorisation, is the paper trail that shows the calendar has ended.

The arithmetic gives a ceiling of about 195 days before any stop, and 255 if the instruction term is doubled. That is 105 days for the authorisation plus 90 for the permit, or 105 plus 120 plus 30. The permit instruction may overlap the landscape procedure in part, since the officer acquires other assents, but the statute does not let us size that overlap. Both figures are Victaura arithmetic.

The authorisation also carries its own expiry clock. It is effective for five years under Article 146, paragraph 4. The same paragraph provides that works begun within the five years may be completed within the following year. It also provides that the five years run from the day the building title becomes effective, unless the delay in issuing that title is attributable to the applicant. Delay in the permit phase caused by the administration therefore costs carrying time but does not consume the life of the authorisation. Delay caused by the applicant can.

90 days
ordinary building permit on statutory terms, 60 days of instruction plus 30 days for the final act (40 after a 10-bis notice); the instruction term doubles for particularly complex projects. Measured in law, not observed.

Source: Italy, DPR 380/2001 (Testo Unico Edilizia), Articolo 20

On a constrained lakefront, silence can form the building permit only once the landscape authorisation is in hand. The landscape step itself ends on an act.

Victaura Research
5 years
effective life of a landscape authorisation, counted from the day the building title becomes effective unless the delay is attributable to the applicant; works begun within it may be completed within one year of expiry. Measured in law.

Source: Italy, D.Lgs 42/2004, Articolo 146, comma 4; Soprintendenza Parma e Piacenza, procedure guidance

Theoretical versus actual

The gap between the theoretical calendar and the real one is the most useful number in this market, and it is not published. We looked for a measured series of landscape authorisation durations by Soprintendenza or by lake comune and did not find one. The World Bank's Doing Business series measured construction permitting, but it modelled a warehouse, not a protected villa, and it does not isolate the landscape step. Nothing we found measures what this paper needs.

What exists is practitioner experience. The companion paper places a substantial restoration of a protected lakefront villa at 12 to 24 months from application to executive title. That is an industry estimate, not an audited series. Against a 195-day ceiling it implies a multiple of roughly 1.9 to 3.7, which is Victaura arithmetic on an unaudited range. The width of the range is itself the honest finding.

The sources of the gap are structural, but their weights are unknown. Suspensions, 10-bis exchanges, commission meeting calendars, redesign after observations and the sequencing of the permit all sit between the statutory terms and the elapsed time. Some part of the 12 to 24 months may also fall before day 0, in design and informal dialogue, and no statutory count includes it. We cannot say how much. Anyone who quotes a single split is guessing.

The useful measure is therefore per file, not per market. A market average would hide the variation that matters, which is between comuni, between design languages and between counterparties. A principal can obtain a dated file from a specific operator on a specific parcel. That file is a sample of one, but it is a sample of one that is real and third-party stamped, and it is what a market series would have been built from.

12-24 months
typical application-to-executive-title duration for a substantial protected lakefront restoration. Industry estimate, unaudited and unpublished; carried from Victaura's companion paper, directional only.

Source: Victaura Research, The Landscape Constraint on Lake Como (industry experience, directional)

Weak points, honestly disclosed

The terms were read from consolidated reproductions and official guidance, not from the consolidated text on Normattiva. The statutory numbers come from a legal-database reproduction of Article 146 and Article 20 of DPR 380/2001, from the text of DPR 31/2017 and from Soprintendenza guidance pages. Secondary sources disagreed in one place. Some older summaries give 25 days for the Soprintendenza in the simplified track, which was the term under the repealed DPR 139/2010, while the DPR 31/2017 text reproduced above gives 20. We used 20. Counsel should confirm every term against the current text.

Expiry of a term does not mean what the calendar implies. A term binds the administration, but the consequence of a missed term differs by step and is contested in case law. We did not survey the case law. We cite two rulings only as directional and one, Consiglio di Stato no. 2487/2023, from its full text. The 60-day rule in paragraph 9 lets the comune proceed. Under that judgment, an opinion arriving after 45 days is no longer binding; what effect it keeps, and how the comune should weigh it, is a question for lawyers, not for this table.

Comune-level variables are unverified. Whether each lake comune has aligned its planning with the regional plan, how often each commission meets and how each applies the complexity doubling were not checked comune by comune. Each can move the calendar by weeks. The paper describes the frame, and the frame does not replace a per-comune review.

Other bodies are not modelled. Hydraulic and hydrogeological review, seismic filing, any lake-domain concession for a boathouse or jetty, and appeals to the administrative court each run their own clocks. Third-party challenges are excluded as well. The calendar covers the two central procedures only, and a real programme adds to it.

Nothing here is a statement about Victaura's own files. We do not publish internal durations, and the figures above describe the statute and reported industry experience. The law as read here is the law as we understood it in September 2026, and the terms in this area are amended often.

The theoretical calendar is the fastest lawful path, not the expected one. Underwrite the file, not the statute.

Victaura Research

What the allocator should ask for

Ask for the dated file, and ask for it in the order of the calendar. The list is short. The application protocol date. The date of transmission to the Soprintendenza. The date and content of any request for additions. The date of the opinion. Any 10-bis notice and the reply. The authorisation date. The permit filing date and the date of the final act, or of the certificate that the terms have lapsed. Each is a stamped record, and none of them requires the operator to disclose anything commercial.

Then compute three ratios from it. The first is elapsed days against statutory days at each step. The second is the number of stops. The third is the share of elapsed time that sits with the administration against the share that sits with the applicant. If delay clusters in the administration's steps, the risk is at comune level. If it clusters in the applicant's answers, the risk is in design and preparation. The two call for different judgements about the counterparty.

Price the gap, not the ceiling. The statutory 105 and 195 days are the fastest lawful path, and they are a poor input for a financing plan. A holding period that is underwritten on the observed calendar of a comparable file is defensible. One underwritten on the statute is a hope. The carrying cost of the asset runs through every day the file waits, whichever party is responsible for the wait.

A calendar does not say whether a scheme will be approved. Approval is a design question, and the calendar is a time question. A clean calendar on a modest scheme says little about a larger one. What the calendar does show is whether the operator files complete applications, answers requests promptly and knows the comune it is working in. Those are observable behaviours, and they are worth more than any description of relationships.

Skin in the game disclosure. Victaura, through its parent Greystone B.V. (Netherlands), develops projects on Lake Como (Italy), in Nungwi, Zanzibar (Tanzania), on Gili Air and in Uluwatu, Bali (Indonesia), and holds an off-plan capital position on Al Marjan Island, Ras Al Khaimah (UAE). Readers should assume commentary may be influenced by, or benefit, these positions. This document is classified as marketing material under MiFID II Article 24(3). It is not investment advice.

Revision notes

This article was corrected on 27 September 2026. A check of its figures and attributions against the cited sources found errors, which have been corrected in the text. The full list, with what the article said and what it says now, is in the corrections section at the end.

This article was corrected on 14 October 2026. On late Soprintendenza opinions it cited only a first-instance ruling on a different procedure and left open whether an opinion arriving after 45 days is still binding. It now cites Consiglio di Stato judgment no. 2487/2023, under which such an opinion remains effective but is no longer binding.

Corrections, 27 September 2026

What the article said and what it says now. The published version said that a 24-month permit process would leave roughly three years to begin works and that delay in the permit phase shortens the life of the landscape authorisation. Article 146, paragraph 4 of D.Lgs 42/2004 provides that the five years run from the day the building title becomes effective, unless the delay is attributable to the applicant, and the article now says so. The published version attributed the 60-day term of the simplified procedure to Article 11 of DPR 31/2017; the term is set by Article 10, paragraph 1, with the steps in Article 11. The published version treated a 10-bis notice as a ten-day stop and gave an illustrative 145 days; under Article 10-bis of Law 241/1990 the terms resume ten days after the observations are filed, so the illustration now reads as much as 155 days. The published version left open whether the local commission's opinion is required in the simplified track in Lombardy; Regional Communication 144/2018, as reported by Edilportale, states that it is mandatory, and the article now says so. The published version described SABAP CO-LC as the Soprintendenza for the province of Como; it covers the provinces of Como, Lecco, Sondrio and Varese.

A further review on the same day refined some of the corrections above and fixed further points. The article said that on a site subject to landscape constraint the building permit cannot be formed by silence and always ends with an express act; Article 20, paragraph 8 of DPR 380/2001, as amended by Law 120/2020 and Law 182/2025, provides that silence-assent still forms where the landscape authorisation for the same drawings has already been issued and is still valid, and the text, the calendar table and the pullquote now say so. The article attributed a 25-day Soprintendenza term in the simplified track to an unnamed trade summary; that term comes from the repealed DPR 139/2010, and the article now names it. The article said that an applicant moved from the simplified to the ordinary track had lost 45 days before day 10; DPR 31/2017 sets no ten-day term for that decision, and the article now says only that the statutory ceiling becomes 105 days rather than 60.

References

  1. Italy, D.Lgs 42/2004 (Codice dei beni culturali e del paesaggio), Articolo 146, Autorizzazione
  2. Italy, D.Lgs 42/2004, Articolo 142, Aree tutelate per legge
  3. Soprintendenza Archeologia Belle Arti e Paesaggio per le province di Parma e Piacenza, Autorizzazione paesaggistica (artt. 146-167), procedure guidance
  4. Soprintendenza Archeologia Belle Arti e Paesaggio per l'area metropolitana di Roma e la provincia di Rieti, Procedura di autorizzazione paesaggistica (art. 146 e 149 D.Lgs 42/2004)
  5. Ministero della Cultura, SABAP CO-LC, Soprintendenza Archeologia, belle arti e paesaggio per le province di Como, Lecco, Sondrio e Varese
  6. Italy, DPR 31/2017, Autorizzazione paesaggistica semplificata, Articoli 10 e 11
  7. Italy, DPR 380/2001 (Testo Unico Edilizia), Articolo 20, Procedimento per il rilascio del permesso di costruire
  8. Italy, Legge 241/1990, Articolo 2, Conclusione del procedimento
  9. Italy, Legge 241/1990, Articolo 10-bis, Comunicazione dei motivi ostativi all'accoglimento dell'istanza
  10. Regione Lombardia, Legge regionale 11 marzo 2005 n. 12, Legge per il governo del territorio (Artt. 80-81)
  11. Regione Lombardia, Competenze e procedure paesaggistiche
  12. Regione Lombardia, Piano Paesaggistico Regionale (PPR)
  13. Studio Cerami, Il silenzio-assenso nel procedimento di rilascio di autorizzazione paesaggistica (Consiglio di Stato n. 2640/2021)
  14. Ingenio, Autorizzazione paesaggistica: il parere tardivo della Soprintendenza non è vincolante (TAR Campania n. 4406/2025)
  15. World Bank, Subnational Doing Business, Dealing with Construction Permits in Milan (warehouse methodology)
  16. Edilportale, Autorizzazione paesaggistica semplificata, in Lombardia serve il parere delle commissioni locali (2 November 2018, on Regione Lombardia Comunicato 144/2018)
  17. Italy, DPR 380/2001, Articolo 20, comma 8, consolidated text with amendments (L. 120/2020; L. 182/2025), Bosetti & Gatti
  18. Italy, DPR 139/2010 (repealed), former simplified landscape procedure, 25-day Soprintendenza term
  19. Consiglio di Stato, ruling of 9 March 2023 n. 2487 (Article 146 Soprintendenza opinion deadlines)

The images in this article are computer-generated illustrations, not photographs.

The information on this website is provided for informational purposes only and does not constitute an offer, solicitation, or financial advice. Indicated returns are estimates and are not guaranteed; past performance is not indicative of future results. Capital invested is at risk.

Considering an allocation to luxury real estate in the locations we operate? Speak to us about our current and upcoming projects.

Speak to Victaura →

Related insights

Illustration of the facade of an old lakeside villa under restoration, a craftsman's hands matching original stucco, scaffolding and a plumb line

Value-Add Methodology

Lake Como Villas: The Conformity Test

On Lake Como the villa a principal buys is almost always an existing building, so its legitimate state decides what can be restored and whether the deed passes. This article sets out the order of tests, from titles and condoni to the survey, the cadastral plan, the Salva Casa tolerances and the binding landscape opinion, and ends with the clause for the preliminary contract.

October 6, 202618 min read

Illustration of a pair of green rubber boots on the wet stone step of a lakeside villa's side door, a closed umbrella hooked beside them, wisteria on the wall and the lake misty beyond on a rainy morning

Value-Add Methodology

Lake Como Property Managers: What the Law Asks

On Lake Como, a manager who collects a short-let rent for an absent owner takes on duties under Article 4 of DL 50/2017, the Civil Code rules on mandate and the national tourist identification code. This article reads the texts as at 25 October 2026, says where they are moving, and stops before any personal question of tax or law.

November 1, 202619 min read

Lake Como protected lakefront landscape

Value-Add Methodology

Lake Como Landscape Constraint: Why It Is Hard to Build

The constraint is not regulation. The constraint is the law itself, written in 2004, codifying landscape protection that dates back to Law 1497/1939 and, for the 300-metre lake band, to Law 431/1985 (the Legge Galasso). On Lake Como, the 300-metre landscape band, the *autorizzazione paesaggistica* under Article 146, the Lombardia regional plan and the municipal regolamenti together set a permitting environment that filters out most new supply by design. For a value-add project, that filter sets both the timeline and the product that can be delivered.

March 4, 202622 min read